DRAFT GRID CAPACITY ALLOCATION RULES Member Comments

THE MAIN ASPECTS OF THE DRAFT GRID CAPACITY ALLOCATION RULES DISCUSSED IN THIS CONSULTATION PAPER

The main aspects of the draft Grid Capacity Allocation Rules discussed in this consultation paper include the following:

i. Principles of the Grid Capacity Allocation Rules
ii. Connection process requirements
iii. The queuing procedure

NERSA has not yet formed any opinions on the main aspects addressed in this consultation paper. However, it is raising these issues to encourage stakeholders to provide their opinions and input. Stakeholder feedback will assist NERSA in making a well-informed decision.

PRINCIPLES OF THE GRID CAPACITY ALLOCATION RULES

The principle of the rules is that network service providers must allow non-discriminatory access to ensure fair, transparent, equitable and open access to the grid to give effect to the first ready, first served principle.

Documents


Market Segment
System Size
Total Capacity
Residential
0 - 30 kWp
--
Commercial and Industrial (C&I) - SSEG
30kWp - 1MWp
--
C&I Large Scale and utility scale
1MWP - 50MWp
--
Utility Scale
> 50MWp
--
TOTAL
--